Country Profiles: Zambia

Cumulative Public Sector Loans as of June 18, 2008

Project Loans millions of US dollars
Agriculture & agro-industry 3.500
Education 16.000
Energy 20.000
Health 5.600
Industry -
Multi-sectoral and other -
National Development Banks 15.000
Telecommunications -
Transportation 39.500
Water Supply & Sewerage 4.000
TOTAL 103.600

Recently Concluded Loan Agreements

For greater detail on the project/program or information on procurement opportunities, requests must be addressed directly to the executing agency (ies) of the project/program.

November 20, 2007
Copperbelt Feeder Road Rehabilitation (US$6 million)
Purpose:
To rehabilitate feeder roads in impoverished agricultural areas in the Copperbelt province to ease the movement of produce and inputs
Activities:
  • rehabilitation of 40 feeder roads, totaling 768 km;
  • installation of drainage works;and
  • consultancy services.
Project cost:
US$13 million
Co-financiers:
BADEA, Government of Zambia

Executing Agency:
Road Development Agency
Implementation period:
3 years

December 13 , 2006
Water Supply Project (US$4.0 million)
Purpose:
To rehabilitate and expand water supply networks in the Copper Belt, Luapula, and Northern provinces.
Activities:
  • procurement and installation of 49 km of water distribution pipes with diameters ranging from 150-500 mm;
  • installation/rehabilitation of pumps, sand filters and reservoirs;
  • carrying out of repairs works; and
  • consultancy services.
Project cost:
US$10.72 million
Co-financiers:

Arab Bank for Economic Development in Africa, Government of Zambia

Executing Agency:
Ministry of Local Government and Housing
Implementation period:
3.5 years

HIPC Debt Relief  millions of US dollars
Purpose: HIPC II 6.00
TOTAL 6.00