November 5, 2008
São Tomé Water Supply (US$2.5 million) |
| Purpose: |
| To build and rehabilitate infrastructure at the country's main water intake sources; the Agua Agriao and Agua Amoreira /td>
|
| Activities: |
- construction of water treatment stations;
- installation of pipe networks and additional household connections; and
- repair and constructions of reservoirs.
|
| Project cost: |
| US$8.25 million |
| Co-financiers: |
| BADEA, Government of São Tomé and Principe |
| Executing Agency: |
| Ministry of Infrastructure, Natural Resources and Energy |
| Implementation period: |
| 3½ years |