Country Profiles: Egypt

Cumulative Public Sector Loans as of June 18, 2008

Project Loans millions of US dollars
Agriculture & agro-industry 30.000
Education 20.000
Energy 107.430
Health 10.000
Industry -
Multi-sectoral and other -
National Development Banks 8.750
Telecommunications -
Transportation -
Water Supply & Sewerage -
TOTAL 176.180

Recently Concluded Loan Agreements

For greater detail on the project/program or information on procurement opportunities, requests must be addressed directly to the executing agency (ies) of the project/program.

December 11, 2007
El Tebbin Power Plant (US$40 million)
Purpose
To meet the growing demand for electricity in Cairo City
Activities
  • demolition of existing plant and preparation works for new site;
  • construction of new plant including two steam turbine units with a capacity of 350 MW each;
  • installation of waster water treatment system; and
  • engineering and consultancy services.
Project cost
US$595 million
Co-financiers
World Bank, Government of Egypt
Executing Agency
Egyptian Electrical Holding Company
Implementation period
4 years


BOP Support Loans millions of US dollars
TOTAL 14.45